45InRow RD Operation and Maintenance
Quarterly Preventive Maintenance
* Perform all the Monthly Preventive Maintenance items and the items below.
Prepared By: _________________________________
Model Number: _______________________________
Serial Number: _______________________________
Date: ______________________________________
Mechanical
Electrical Hazard: Turn off the cooling unit and disconnect all power sources. Perform Lockout/
Tagout procedures before performing any electrical or mechanical service. Wear appropriate
personal protective equipment when checking hazardous voltages.
Verify that the fan hardware is tight.
Clean the condensate drain line.
Clean the dust from door perforations.
Clean the dust from fan bezels.
Functional tests
Verify the cooling operation mode is functioning properly.
Semi-Annual Preventive Maintenance
* Perform all the Monthly/Quarterly Preventive Maintenance items and the items below.
Prepared By: _________________________________
Model Number: _______________________________
Serial Number: _______________________________
Date: ______________________________________
Cleanliness
Check the cleanliness of the evaporator coil. Clean if required.